New Construction Project Update – Nov. 2022
There has been a lot of activity at CityLink’s facilities on NE Jefferson the past month! The latest updates from the new paint/body shop (Phase A) and the new maintenance and administrative facilities (Phase B) construction project for CityLink, are below. Phase A – Rear Building (Paint/Body Shop): Phases B, C, & D: You will […]
Posted: November 22, 2022 | View More »
Passenger Link – October 2022
CityLink Construction Project Update Work on the new CityLink maintenance, operations, and administrative facilities (Phase B) construction project has really progressed over the past few months. The crew at River City Construction has formed the garage building low wall, installed insulation at the garage building low wall, and poured the garage building footings. They are […]
Posted: November 2, 2022 | View More »
New Construction Project Update – Oct. 2022
The latest updates from the new paint/body shop (Phase A) and the new maintenance and administrative facilities (Phase B) construction project for CityLink, are below. Phase A – Rear Building (Paint/Body Shop): Punch List – 95% complete Close out documents – 99% complete from subcontractors Design team reviewing River City Construction (RCC) submitted a Preliminary […]
Posted: October 27, 2022 | View More »
New Construction Project Update – Sept. 2022
The latest updates from the new paint/body shop (Phase A) and the new maintenance and administrative facilities (Phase B) construction project for CityLink, are below. Phase A – Rear Building (Paint/Body Shop): Punch List – 90% complete Close out documents – 98% complete from subcontractors, currently in design team’s hands Owner Training – Working with […]
Posted: September 26, 2022 | View More »
Library Card Partnership Video Shoot Behind the Scenes
On August 25, 2022, CityLink participated in a quick and fun video shoot with the participating public libraries to promote the #FineFareFareFree campaign for the month of September. During the shoot, a CityLink bus visited all of the participating libraries: Peoria Heights Public Library Peoria Public Library Main Branch Lincoln Branch Fondulac District Library Pekin […]
Posted: September 8, 2022 | View More »
New Construction Project Update – Aug. 2022
The latest updates from the new paint/body shop (Phase A) and the new maintenance and administrative facilities (Phase B) construction project for CityLink, are below. Phase A – Rear Building (Paint/Body Shop): Punch List – 80% complete Close Out Documents – 95% complete, pending test & balance report Owner Training – ANJ/K-Com & Pipco completed […]
Posted: August 30, 2022 | View More »
New Construction Project Update – Jul. 2022
The latest updates from the new paint/body shop (Phase A) and the new maintenance and administrative facilities (Phase B) construction project for CityLink, are below. Phase A – Rear Building (Paint/Body Shop): Punch list, close out documents, and owner training Control panel for Paint Booth being completed Currently 98% complete Phases B, C, & D: […]
Posted: July 28, 2022 | View More »
Passenger Link – July 2022
GPMTD Board Names Chris Ahart Chair and Welcomes Don Knox Members of the GPMTD Board of Trustees selected Chris Ahart as the new Board Chair at the May 2, 2022 board meeting. This is Ahart’s first term as Board Chair. Ahart represents the Village of Peoria Heights, and he was appointed to the GPMTD Board […]
Posted: July 25, 2022 | View More »
CityLink Transit Center Solar Panel Installation Project Update – June 2022
Since May, the CityLink Transit Center solar installation project has moved right along with finalization of the optimizer installation, DC conduit runs to the junction box, and module installation! The cabling and roof piping are getting dressed now, and then Roy Keith Electric (RKE) will be prepping for the equipment rack that will be assembled […]
Posted: June 24, 2022 | View More »
New Construction Project Update – Jun. 2022
It has been a while since we’ve provided an update, but a lot has happened in the last several weeks! The latest updates from the new paint/body shop (Phase A) and the new maintenance and administrative facilities (Phase B) construction project for CityLink, are below. Phase A – Rear Building (Paint/Body Shop): Subcontractors are working […]
Posted: June 23, 2022 | View More »