New Construction Project Update – Nov. 2022

There has been a lot of activity at CityLink’s facilities on NE Jefferson the past month! The latest updates from the new paint/body shop (Phase A) and the new maintenance and administrative facilities (Phase B) construction project for CityLink, are below.

Phase A – Rear Building (Paint/Body Shop):

  • Punch List – 97% complete
  • Close Out Documents – 99% complete from subcontractor
    • Design team reviewing
  • Dries Plumbing/ANJ Electric
    • New breaker is in and installed
    • Pending owner training
      • River City Construction (RCC) coordinating with CityLink
  • Currently 99% complete on Phase A

Phases B, C, & D:

  • ANJ installing duct bank west of garage
  • Mid-States Precast – Installed precast panels
    • Will be back to clean and caulk panels
  • Hanley (United Ironworkers) – Erecting garage building steel & decking
  • RCC (L2 Structures) – Installed tent
  • Phase BCD – 26.15% construction complete

You will find updated photos below that were taken over the past several weeks. A new time-lapse that was taken between October 17, 2022 and and November 9, 2022 is also available below.