New Construction Project Update – Nov. 2022
There has been a lot of activity at CityLink’s facilities on NE Jefferson the past month! The latest updates from the new paint/body shop (Phase A) and the new maintenance and administrative facilities (Phase B) construction project for CityLink, are below.
Phase A – Rear Building (Paint/Body Shop):
- Punch List – 97% complete
- Close Out Documents – 99% complete from subcontractor
- Design team reviewing
- Dries Plumbing/ANJ Electric
- New breaker is in and installed
- Pending owner training
- River City Construction (RCC) coordinating with CityLink
- Currently 99% complete on Phase A
Phases B, C, & D:
- ANJ installing duct bank west of garage
- Mid-States Precast – Installed precast panels
- Will be back to clean and caulk panels
- Hanley (United Ironworkers) – Erecting garage building steel & decking
- RCC (L2 Structures) – Installed tent
- Phase BCD – 26.15% construction complete
You will find updated photos below that were taken over the past several weeks. A new time-lapse that was taken between October 17, 2022 and and November 9, 2022 is also available below.