New Construction Project Update – Feb. 2022

The latest updates from the new paint/body shop, which is Phase A of the new maintenance and administrative facilities construction project for CityLink, are below.

Phase A – Rear Building (Paint/Body Shop):

  • Peoria Metro prepped & poured slabs
  • Dries Plumbing set the trench drains
  • PIPCO installed ductwork, heaters, gas piping and insulation
  • A.N.J. Electric has been running conduit and getting panels ready for install
  • Set roof top units and skylights
  • A lot is happing over the next couple months

Phases B, C, & D:

  • Bid opening went well, River City Construction & GPMTD are working through scopes and hopefully looking for approval in March
  • Currently 50% complete on Phase A

You will find update photos below that were taken in February from a Bradley Construction Management class site visit and of the exterior and interior of the new paint/body shop. Unfortunately there is, once again, no new timelapse video this month.

  • Phase A – Rear Building (Paint and Body Shop)
    • Final Completion Expected April 19, 2022
  • Phase B – Admin/Maintenance Shop & Visitor Parking
    • Out for Bid – December 2021
    • Demo of 1978 Building – April/May of 2022
    • 1 year for site & building construction phase – April/May of 2023
    • Final Completion Expected December 2023
  • Phase C – South Storage Building Renovation
    • Out for Bid – December 2021
    • Final Completion Expected December 2023
  • Phase D – Annex
    • Out for Bid – December 2021
    • Final Completion Expected December 2023

As construction continues, updates will be made on the progress through our website and YouTube channel.