New Construction Project Update – December 2021
We have four walls! The latest updates from the new paint/body shop, which is Phase A of the new maintenance and administrative facilities construction project for CityLink, is below.
- A&H Steel continues installing metal bracing and miscellaneous steel.
- Western has started installing insulated metal panels.
- ANJ Electric & Dries Plumbing did a great job on getting the underground utilities completed for the duct bank across the drive lane from existing south building to new paint booth building.
- Mechanical Ditch – concrete install was completed.
- Peoria Metro moving right along with the retaining wall.
- NE Finch continues to work on grading and backfilling.
- Currently 35% complete on Phase A.
You will find photos below that were taken in early-mid December and a timelapse video from Noevember 14, 2021-December 11, 2021.
- Phase A – Rear Building (Paint and Body Shop)
- Final Completion Expected April 19, 2022
- Phase B – Admin/Maintenance Shop & Visitor Parking
- Out for Bid – December 2022
- Demo of 1978 Building – April/May of 2022
- 1 year for site & building construction phase – April/May of 2023
- Final Completion Expected December 2023
- Phase C – South Storage Building Renovation
- Out for Bid – December 2022
- Final Completion Expected December 2023
- Phase D – Annex
- Out for Bid – December 2022
- Final Completion Expected December 2023
As construction continues, updates will be made on the progress through our website and YouTube channel.
You must be logged in to post a comment.