X
X Alerts
4
14
Track your CityLink bus location in real-time Track Now
Service Alerts
Currently
309-676-4040
4
14

New Construction Project Update – December 2021

We have four walls! The latest updates from the new paint/body shop, which is Phase A of the new maintenance and administrative facilities construction project for CityLink, is below.

  • A&H Steel continues installing metal bracing and miscellaneous steel.
  • Western has started installing insulated metal panels.
  • ANJ Electric & Dries Plumbing did a great job on getting the underground utilities completed for the duct bank across the drive lane from existing south building to new paint booth building.
  • Mechanical Ditch – concrete install was completed.
  • Peoria Metro moving right along with the retaining wall.
  • NE Finch continues to work on grading and backfilling.
  • Currently 35% complete on Phase A.

You will find photos below that were taken in early-mid December and a timelapse video from Noevember 14, 2021-December 11, 2021.

  • Phase A – Rear Building (Paint and Body Shop)
    • Final Completion Expected April 19, 2022
  • Phase B – Admin/Maintenance Shop & Visitor Parking
    • Out for Bid – December 2022
    • Demo of 1978 Building – April/May of 2022
    • 1 year for site & building construction phase – April/May of 2023
    • Final Completion Expected December 2023
  • Phase C – South Storage Building Renovation
    • Out for Bid – December 2022
    • Final Completion Expected December 2023
  • Phase D – Annex
    • Out for Bid – December 2022
    • Final Completion Expected December 2023

As construction continues, updates will be made on the progress through our website and YouTube channel.

First Time Riders CityLift Service Countylink Service Join Our Team