New Construction Project Update – Dec. 2022

There continues to be a lot of activity at CityLink’s facilities on NE Jefferson in the past month! The latest updates from the new paint/body shop (Phase A) and the new maintenance and administrative facilities (Phase B) construction project for CityLink, are below.

Phase A – Rear Building (Paint/Body Shop):

  • Punch List – 99% complete
  • Close Out Documents – 99% complete from subcontractor
    • Design team reviewing
  • Owner Training for compressor
    • Start up training completed
    • Scheduling overall training with CityLink
  • Currently 99% complete on Phase A

Phases B, C, & D:

  • ANJ Electric
    • Backfilled duct bank east of garage
    • Formed & poured CT cabinet & transformer pads
  • JJB Masonry
    • Installed concrete masonary units (CMU) at the elevator shaft #2, garage, and stairwell in the garage
  • Hanley (United Ironworkers)
    • Erecting the three-story building and garage building steel
    • Last beam was officially placed on Dec. 9
  • River City Construction (RCC)
    • Installed temporary doors at wash bay & garage
    • Overhead doors installed in temporary tent structure
  • Currently 29.77% complete on Phases B, C, & D

You will find updated photos below that were taken over the past several weeks. A new time-lapse that was taken between November 14, 2022 and and December 7, 2022 is also available below.