New Construction Project Update – Apr. 2023
Work on the CityLink construction project is really moving along! This month we have several new photos, including some shots of the 2nd and 3rd floors of the three-story building. The latest updates from the new maintenance and administrative facilities (Phase B) construction project for CityLink, are below.
- N.E. Finch
- Backfilling north of admin
- Demo of house on Van Buren
- Grading house lot and graded south end of garage
- United Rebar – Installed rebar at diamond lifts
- Tobin – Installing trench drains in garage
- JJ Braker – Installed concrete masonary unit (CMU) at admin 1st floor, & the garage north wall
- River City Construction
- Installed vapor barrier at south end of garage
- Poured chassis wash, & north & north ends of garage slab on grade (SOG)
- Set door frames at admin 1st floor
- ANJ Electric – Installed temporary lights at admin 1st floor
- Bedrock Painting – Installed block filler at mezzanine & south garage wall
- PIPCO – Installed hangers and ductwork at admin 2nd floor
- Wright-Way – Installing exterior metal framing at admin
- Currently 38.12% complete on Phases B, C, & D
You will find several updated photos below that were taken over the past several weeks. A new timelapse video should be available soon.
You must be logged in to post a comment.